The goal of this project was to make essential repairs to the platform superstructure, blockwork, and coping stones at Grange Park Station

This job consisted of many aspects, each with their own challenges. We completed the works within five, 27-hour, weekend possessions, safely and to a high standard.


At Grange Park Station, both platforms required strengthening and repair works.


This consisted of Coper repositioning to new "x" and "y" dimensions, steel strengthening works to cross walls & platform superstructure and resin injection & grout repairs to cross walls