20230128_100326

There were two sets of work for our team at Stansted Tunnel, the first was replacing old rusted walkway support legs with new ones and the second was exposing defects in the tunnel ceiling to enable grouting repair works to commence. At both jobs, our team utilised the best equipment for the job and their years of experience to complete the works efficiently, as they were under pressure due to restricted time windows. The team worked alongside other teams from various different contractors, displaying excellent communication and ability to adapt to new working environments.



IMG_2830
20230128_121733